By Bankero staff
The Bangko Sentral ng Pilipinas-owned Philippine International Convention Center (PICC) was late in submitting ₱174 million worth of contracts and purchases for government audit in 2025, the same year it spent heavily on renovations under the chairmanship of BSP Governor Eli Remolona Jr.
The Commission on Audit (COA) found that 84 of 108 contracts and purchase transactions, or nearly eight out of every 10, were submitted beyond the required five working days.
Some records were delayed by as much as 46 days, while reports confirming the delivery of goods and services arrived as much as 515 days late, or more than 17 months beyond the deadline.
The delays prevented government auditors from checking transactions promptly and identifying possible problems before they became harder to correct.
Of the ₱174 million flagged, ₱158.46 million involved 28 contracts, ₱9.04 million covered 30 requests for services, and ₱6.53 million involved 26 purchase orders.
The findings came as PICC underwent a major makeover ahead of its 50th anniversary and the Philippines’ hosting of the 2026 ASEAN Summit.
Financial statements show that the BSP approved a ₱1.134 billion capital budget for PICC in 2025, up from ₱251.04 million the previous year.
The BSP Monetary Board also approved a supplemental capital budget specifically for the convention center’s repair and renovation project.
Of the ₱1.134 billion annual capital budget, PICC recorded ₱561.45 million in actual disbursements during the year and returned ₱59.91 million in unused funds to BSP. Its remaining capital-budget balance, including funds carried over from earlier years, reached ₱783.29 million at year-end.
PICC closed for approximately six months before reopening in September 2025, following improvements to its convention halls, meeting rooms, buildings, audiovisual systems and other facilities.
President Ferdinand Marcos Jr. attended the reopening with Remolona and PICC general manager Nicolette Ann P. Cruz , who took over in November 2024.
At the ceremony, Remolona described the renovation as part of the central bank’s responsibility to preserve the landmark convention center.
“The renovation of the PICC was meant to preserve a landmark of Filipino ingenuity,” Remolona said.
But COA’s examination of the convention center’s procurement records uncovered problems beyond missed deadlines.
Auditors found that PICC failed to submit several documents needed to check whether contracts awarded through competitive bidding had followed government rules.
These included records of meetings with prospective bidders, the opening of bids, and the technical and financial proposals of winning contractors.
COA said the missing documents made it difficult to review the bidding process and promptly identify possible irregularities.
The agency also questioned PICC’s handling of delivery records.
Government rules require inspection and acceptance reports to be submitted to auditors within 24 hours after goods or services are accepted.
PICC officials claimed they submitted delivery reports along with invoices, contracts and other supporting documents.
However, COA found that only the daily delivery reports were consistently submitted, and even those were delayed by six to 515 days.
The audit warned that the delays weakened safeguards against “irregular, unnecessary, excessive, extravagant, or unconscionable expenditures.”
PICC’s procurement office blamed the delays partly on its practice of sending documents electronically in batches rather than immediately after transactions.
It also said some bidding documents were kept in separate files because sending all attachments could exceed available storage and transmission limits.
COA traced the problems to poor monitoring and weak coordination among the offices handling purchases, deliveries and supporting records.
The findings added to PICC’s financial troubles during the year.
The convention center posted a ₱163.44 million net loss in 2025, reversing a ₱170.38 million profit in 2024, as rental income plunged 81 percent following its temporary closure.
It also spent ₱398.09 million more cash on operations than it generated, while the amount it owed the BSP climbed to approximately ₱1.44 billion.
COA ordered tighter monitoring of procurement records, complete submission of bidding documents and stricter compliance with reporting deadlines. PICC management agreed to implement the recommendations.
ALSO READ:
LANDBANK touts clean audit opinion, P98 billion in dividends amid COA scrutiny
DBP disputes selective COA reporting, cites unqualified opinion amid P4.09B loan scrutiny
P1.24B in limbo: COA flags DBP’s unverified MRT-3 investment valuation